Tunnel jacking is MBTA's fault ... NOT
I keep hearing town hall people blame the MBTA for the switch from tunnel jacking to cut & cover. From the sequence of events that I witnessed, it was the town's own fault that the project started off with jacking.
PARE vs NITSCH
It all started with the PARE to Nitsch switch at the design stage which was a very unconventional move. It's all described here
FIRST MEETING WITH NITSCH
At the first meeting after being hired, Michalak made mention of tunnel jacking. The committee members expressed some surprise saying they had expected cut & cover. Their surprise surprised me since the Nitch bid was so much about jacking. Michalak made it clear that the method to be used was jacking.
SECOND MEETING WITH NITSCH
At this meeting, Michalak talked about jacking but now he implied that he was obeying the town's wish to use jacking. This was quietly accepted by the committee members. I was slack jawed at how responsibility for jacking had been smoothly switched from Nitsch to the town.
From that point onward, the town was held responsible for the choice of jacking until, some time later, Michalak showed up and ruefully explained that the MBTA was demanding tunnel jacking for all projects that went under the rails. He said that the MBTA officer (Chief of Rail Operations) had explained that the MBTA engineers did not approve of soil compaction issues seen when using cut & cover. Michalak even presented some figures having to do with this compaction issues around tunnel structures.
Because of the evolving story line about jacking, I was distrustful so I contacted the MBTA's Chief Engineer who told me that there was no such demand for using jacking in all projects under the rails. He said that the decision on method was "on a case by case basis". Here's a detailed post about this that I wrote at the time.
And there you have it, how the choice of the very expensive tunnel jacking method came about!
EPILOGUE
Nobody seemed to mind that jacking - this very expensive method - also
happens to be highly unsuitable to our soil type and high water table
(much later, Nitsch's Michalak revealed this at the MassDOT Public Hearing).
With jacking method seemingly secured, planning continued. I listened to the CPPC discuss widening the underpass from a pedestrian-bike walkway (10-12 ft) to a 2 vehicle road (~40 ft). This would raise the cost to astronomical levels likely satisfying the demand of a committee member who arrived several times saying "We must increase the budget!'. But it would also increase the potential damage to our homes' structures and drive us crazy with the constant hammering at night* for months.
But as Nitsch's subcontractor Sean Sanger said to me: "Nothing will be allowed to stand on the way of a multimillion dollar project"
*plan was to jack at night when the trains were not running. Jacking consists of smacking a piston against the soil every ~2 minutes making progress of a 1-2 inches each time. Largest jack makes an opening of ~20 ft so widening the underpass to 30-40 ft means that 2 sets of pits for the jack would have to be excavated. Double the time, double the expense, double the sleepless nights.