A Tangled Web
Oh, what a tangled web we weave, when first we practice to deceive " Abutters have asked for the engineering plan for the 25% design submittal or what Stanton called the "revised" 25% design. Since, on January 10, Michalak (PE or Project Engineer) announced that the Public Hearing had been scheduled then this revised plan had to exist at that date. JS requested it from MassDOT Public Records on Februaru 23 and waited and waited. Finally around March 14-15, JS received documents: the original, unrevised 25% design submission from November 2021, ROW papers, and the bridge worksheet with a submission date of January 24. (It's a tunnel or underpass but technically it becomes a bridge). Note that it is the original 25% not the revised design so it still has a figure indicating that the tunnel will be "jacked". The other fun part is that the bridge worksheet was submitted on January 24th not by December 21, 2023 as Michalak had said at the Dec...